Skip to Main Content
IBM Data and AI Ideas Portal for Customers


Shape the future of IBM!

We invite you to shape the future of IBM, including product roadmaps, by submitting ideas that matter to you the most. Here's how it works:

Post your ideas

Post ideas and requests to enhance a product or service. Take a look at ideas others have posted and upvote them if they matter to you,

  1. Post an idea

  2. Upvote ideas that matter most to you

  3. Get feedback from the IBM team to refine your idea

Help IBM prioritize your ideas and requests

The IBM team may need your help to refine the ideas so they may ask for more information or feedback. The product management team will then decide if they can begin working on your idea. If they can start during the next development cycle, they will put the idea on the priority list. Each team at IBM works on a different schedule, where some ideas can be implemented right away, others may be placed on a different schedule.

Receive notification on the decision

Some ideas can be implemented at IBM, while others may not fit within the development plans for the product. In either case, the team will let you know as soon as possible. In some cases, we may be able to find alternatives for ideas which cannot be implemented in a reasonable time.

Additional Information

To view our roadmaps: http://ibm.biz/Data-and-AI-Roadmaps

Reminder: This is not the place to submit defects or support needs, please use normal support channel for these cases

IBM Employees:

The correct URL for entering your ideas is: https://hybridcloudunit-internal.ideas.aha.io


Status Under review
Workspace Db2
Created by Guest
Created on May 5, 2022

Redirected Restore on STANDBY for STOGROUP expansion

Case number: TS008472518

Our database was 42TB and the file system were 45TB across 12 file systems. I wanted to expance the total storage to TB by adding 12 additional file systems. I took a backup and did a re-directed restore on standby with 24 file system in the same storage group on pre-prod environments. After the restore, I started standby, and I see no issues and took over as primary; Carried the same process on new standby (old primary)

Time taken: 8 hours each; Total file system used: 42 TB out of 60TB.

IBM disagreed with this approach and wanted me to add the new file system to the storage group and rebalance each file system. I was completed to expand the file system to 90TB as DB2 required two copy of the data during the rebalance
Time to rebalance: 120 hours; additional space requirement: 45TB
System was slow during these 120 hours.

RFE: IBM/DB2 team should allow the approach I took which is simple and robust. IBM can put limitation that no DDL/ALTER can be done on the tablespaces till the standby is not converted to Primary, after the restore.